Network Switch Replacement Project

Overview

Network switches across campus will be upgraded over the course of 18 months as part of a normal life-cycle replacement schedule. 

Project Status

Active - In progress

Replacement Process Description

OIT will upgrade network switches across campus as part of a normal life-cycle replacement schedule. As buildings across campus are scheduled for replacement, they will be added to the Scheduled Switch Replacements spreadsheet below. 

The replacements will take place on a building-by-building basis from 4:00 a.m. to 7:00 a.m. on business days by OIT staff. This will cause network outages, for both wired and Wi-Fi networks, including Cisco VoIP phones, from 30 minutes to 160 minutes, based on the number of switches being replaced.

*Please note: Ordering new or changing existing network services will be frozen for two weeks prior to a building’s switch replacements in order to ensure service continuity. 

Scheduled Switch Replacements

Building Week Freeze Dates Work Dates Status Notes
BIOT-E 1 Feb 17 - Mar 4 Mar 2-4 Completed
LESS 1 Feb 17 - Mar 5 Mar 5 Completed
IEC 2 Feb 24 - Mar 9 Mar 9 Completed
PRL3 2 Feb 24 - Mar 10 Mar 10 Completed
PENN 2 Feb 24 - Mar 11 Mar 11 Completed
TB01 2 Feb 24 - Mar 12 Mar 12 Completed
CLRE 2 Feb 24 - Mar 12 Mar 12 Completed
DALW 3 Mar 2-18 Mar 16-18 Completed
MKNA 3 Mar 2-19 Mar 19 Completed
MCKY 4 Mar 9-24 Mar 23-24 Completed
ALUM 10 Apr 20 - May 4 May 4 Completed
ALMG 10 Apr 20 - May 4 May 4 Completed
REC 10 Apr 20- May 12 May 4-8 Completed
RAMY 10 Apr 20- May 12 May 8-12 Completed
FH 11 Apr 27-May 14 May 14 Completed
FHPB 11 Apr 27-May 15 May 15 Completed
CARL 12 May 4-18 May 18 Completed
GOLD 12 May 4-26 May 19-26 Completed
STTB 13 May 11-28 May 28 Completed
STSB 13 May 11-29 May 28-29 Completed
STAD 14 May 18-Jun9 Jun 1-9 Completed
PORT 15 May 25-Jun 12 Jun 11-12 Completed
MUEN 16 Jun 1-19 Jun 15-19 Completed
CHAMP 17 Jun 8-26 June 22-26 Completed
IPRC 17 Jun 8-26 Jun 26 Completed
ECES 18 Jun 15-30 Jun 29-30 Completed
NCWIT 18 Jun 15-Jul 2 July 2 Completed
WVC 19 Jun 22-Jul 7 Jul 6-7 Completed
WILD 19 Jun 22-Jul 10 Jul 9-10 Completed
KOBL 20 Jun 29 -Jul 13 Jul 13 Completed

*Please note: Dates are subject to change. 